• Home
  • Services
  • About Us
  • Contact
  • Blog
  • Home
  • Services
  • About Us
  • Contact
  • Blog
  WHITE OWL DATA
  • Home
  • Services
  • About Us
  • Contact
  • Blog

Blog

    Author

    Val Gourd

    Archives

    July 2019

    Categories

    All

    RSS Feed

Back to Blog

Construction Applications for Payment

7/15/2019

 
​How to correctly complete the AI G702/G703.
Construction Application for Payments
 
This system was created to provide a standard method of billing for contractors to get paid.  The form allows the contractor to invoice, and the architect to certify that the work is complete and correct.  If the application is completed correctly (and the work is too!), the architect’s signature is the signal to the owner to release payment to the contractor.  (Line 8 is the amount due).  In addition, the architect can certify a different amount due. 
 
In order to fill out this form – you must,
  1.  Ignore unprocessed change orders – include them and your invoice will be denied;
  2. Ignore money that is still outstanding from previous applications for payment - include it and your invoice will be denied
 
The following information will explain what each section of the forms should contain and how to correctly fill out an AIA G702 - Application for Payment and G703 - Continuation sheet.
 
G702
 
AIA Form G702 - Contractors Application for Payment is a summary of the information being submitted on the Continuation Sheet (G703).
 
 
 
It requires the contractor to show the status of the construction contract to date; including the Original Contract Sum, Net Change by Change Orders, Contract Sum to Date, Total Completed and Stored to Date, the amount of Retainage (if any) on Completed Work, Stored Material, and Total Retainage to date, the Total Earned Less Retainage, the Total of Previous Certificates for Payment, Current Payment Due, Balance to Finish, including Retainage, and a summary of Current and Previous Change Orders - indicating if the Change Orders were an Addition to or a Deduction from the Original Contract Amount.  This document must be signed by the contractor and notarized prior to submission. 
HEADER INFORMATION (must be included on each Application for Payment you submit)
To Owner - the name, address, and contact information of the person paying you.
From Contractor - that's you!
Project - the name and location of the project that you are working on; this information is found in the Contract or Subcontract Agreement. 
Via Architect - the name and contact information of the Architect that oversees this job. 
Application No. - when you number your payment applications, give the first one "1" and then count from there. 
If you find that you must revise a Payment Application, do not increase the number - just give it the same number, and then with a bright orange or green highlighter, handwrite REVISED across the top of the header.
Period To - this is the As Of date or the LAST day of the work cycle that you are billing for.
Contract Date - this is the date of your original Contract or Subcontract Agreement
Project # - the Contract or Subcontract number from the Contract or Subcontract Agreement (for example – CP17-1941-2A).  There may be additional project numbers - Federal, State, and Architect Project numbers. 
Distribution To - this indicates a list of who else will receive a copy of the Application for Payment.
Contract for - this is a brief description of the scope of work that is being performed and can be found in the Contract/Subcontract Agreement
SUMMARY OF WORK
Line 1, Original Contract Sum - this is the price that the General Contractor or Project Owner originally agreed to pay you for the work you agreed to do.  This should include all accepted alternatives.  Pull out your contract, look at it, find the amount.  The amount displayed on this line should NEVER change from your first Application for Payment to your last.
Line 2, Net Changes by Change Orders - ok, here it is, the line that causes so much confusion and frustration.  Add up all the Change Orders that have been priced AND FORMALLY APPROVED by the General Contractor or Project Manager. 
Line 3, Contract Sum to Date - add the numbers on Lines 1 and 2 above.  This is your official contract sum as of the date of this Payment Application.
Line 4 Total Completed and Stored to Date - this number comes from the left side of Column G on the G703, this box is the fourth from the left on the bottom row of the last page of the G703.
Line 5, Retainage (three lines) - retention or retainage is usually a specific percentage (5%) of the total contract that is held back by the project owner in reserve to protect the owner’s interest.  Retention is not held in a lump sum, but rather, held at the stated percentage for the amount requested on each application for payment.  Your contract should set the terms of retention including the percentage and when the hold-back will be paid.  (If it does not, you should insist that no retention be withheld.  If the GC failed to specify retention in your contract, do not allow him to use it.  If you happen to be providing a Performance Bond, retention is not justified.  The bond serves the same purpose as retention).

Line 5a, _% of Work Complete - typically, this is 5%. In the blank spot next to the $ sign, you need to write down the dollar value of retention that applies to your completed work.  To figure out this amount, go to the G703 form and add together the values from the bottoms of Columns D and E; multiply this total by 0.1 if the Retainage is held at 10% OR aby 0.05 if the retention is held at 5%.
Line 5b, _% of Stored Materials - repeat the process used for Line 5a, EXCEPT use the value from the bottom of Column F on Form G-703.  Usually, the amount of retention for completed work and stored materials is the same.  
Line 5, Total Retainage - add together the dollar amounts from Lines 5a and 5b if your retention is a fixed amount.  IF your retention varies per line item or phase, then you would not complete 5a and 5b, and instead, just enter the total of Column l on your G703 in this section. 
Line 6, Total Earned Less Retainage - what you have earned OR Line 4 MINUS the Total Retainage on Line 5. 
 
Line 7, Less Previous Certificates for Payment - this is Line 6 from the LAST Payment Application you sent. 
Line 7 causes a lot of confusion; sometimes because GC's and Owners take so long to pay that you end up submitting your next Payment Application before the previous one is paid.  Many people also write down the total payments received to date on Line 7 and ignore pay requests that are being processed.  DO NOT make this same mistake!  The Payment Application doesn't care whether you've been paid or not -- it only cares that you have EARNED additional payments.  Go back and get the last Payment Application that you submitted, write down the dollar amount from line 6 (Total Earned Less Retainage) on that application.  Remember, only the LAST Payment Application is considered.
Line 8, Current Payment Due - take the value from Line 7 and subtract the value of Line 6, the difference is written on Line 8.  This amount represents the amount you should be paid for work earned during this pay period AND any change in Retainage during the period. 
Line 9, Balance to Finish INCLUDING Retainage - take the contract sum to date from Line 3 and subtract the amount from Line 6.  This tells the GC or Owner that he is contracted to pay you an additional amount AFTER paying this application.
Line 9 is another confusing section of the G702 because it "acts" as if all Change Orders have been formally processed and that all previous Payment Applications have been paid in full.  Frequently, Owners and G's only pay a portion of the Payment Application that you submit.  The AIA G702 form NEVER reflects partial (or even full) payments.  It just was not designed to keep track of what has been paid, only what has been earned and invoiced for.
Change Order Summary Table - is straightforward.  You will need to separate the Change Orders that add money to your contract from those that subtract money from your contract. 
 
G703
The G703 Continuation Sheet is also referred to as Page 2 of the Application and Certificate for Payment (G702 form).  It breaks down the contract sum into portions or segments of the work in accordance with a Schedule of Values required by the General Conditions of the contract.
When you look at our plain paper version of the AIA G703; Continuation Sheet, you can see that C should be completed by identifying the various portions of the Project.  The Scheduled Values should be consistent with the schedule of values (Estimate or Bid) submitted to the Architect at the beginning of the project.  This breakdown should be used consistently throughout the project, using multiple pages when necessary. 
HEADER INFORMATION (must be included on each Continuation Sheet page that you submit)
To - the contract owner or the person who will be cutting your checks for payment of work you have performed.
From - the "From" is always you.
Page - the page number of the Continuation Sheet. 
Application No. - same as the Application Number from the header of the G702.
Application Date - the date that you are submitting the Application for Payment.
Period To - should be the same as the Period To date from the header of the G702.
Architects Project No. - the project number that the Architect has assigned to this project. 
 
SUMMARY
Column A - the line numbers are usually simply numbered sequentially 1 through whatever.  Sometimes, you will be asked to make the numbers match the specifications section number found in the specification sheet, alternatively, you may be asked to number each line as 10, 20, 30 etc.
Column B, Description of Work - this column holds a BRIEF description of the phase, portion of work, or cost code.  Examples might include:  Site Work, Plantings, Drainage, Paving, Striping, etc.  If your scope of work is complex, you may wish to match this to the major activities or cost codes from your Estimate/Bid.  NOTE:  Change Orders are added as either separate line items, as they are approved, and you may be asked to display all change orders on a separate Continuation Sheet. 
Column C, Scheduled Value - this is the total amount of money that you were scheduled to receive for this phase of the work or cost code item.  For example, your contract might specify that you will receive $100,000.00 for Site Work. 
 
Column D Work Completed from PREVIOUS Applications - this is the Total of Work Completed from the Previous Applications amounts in Column D & E; or the total dollar amount you requested for this line item up through and including your LAST Application for Payment.  This amount also includes materials that you previously listed as Stored Materials but have now put in place or installed.  Column D does not include any work that you have completed for this period and it does not include any newly stored material. 
Column E, Work Completed THIS Period - the value of Work completed at the time of the current application
Column F, Materials Presently Stored - this is the value of Materials Presently Stored on the Job Site for which you are seeking payment.  This typically refers to the total value of any materials that are currently stored on the jobsite but are not yet installed.
Usually, in order to be paid for stored materials, they must be either physically stored on the job site OR in a bonded, secure storage facility.  In many cases, especially where the government is concerned, you will only be paid for installed materials. 
Column G Total Completed & Stored to Date - the Total of the amounts shown in Columns D, E, & F for each line item. 
 
Percentage Complete - this amount is calculated by dividing Column G by Column C for each line item. 
 
Column H, Balance to Finish - calculate the difference between Column C minus Column G for each line item. 
 
Column l, Retainage (IF Variable Rate) - this column is used ONLY for contracts where retainage rates change on a line-by-line basis, where retainage is different on different sections of the contract OR when retainage changes throughout the life of the contract.  It DOES NOT need to be completed for contracts that have a consistent rate of retainage held over the entire contract. 
Change Orders
Approved contract Change Orders are listed separately, either on their own Continuation Sheet or at the end of the original Schedule of Values.
 
 
2 Comments
Read More
Home Construction link
3/19/2020 06:11:57 pm

This article will help you understand the basic home construction process. Although this article only offers a brief overview, it will still help you get a general idea of how the construction process works.

Reply
first floor additions sydney link
7/13/2022 06:54:15 pm

When payments are made during the course of the task at predetermined intervals and are spaced out over the project, pay applications are often employed. Since the American Institute of Architects (AIA) creates one of the most widely utilized pay programs, it is also known as AIA billing. With progress billing, contractors submit a fresh payment request prior to the end of each pay period for the labor performed and supplies acquired during that time. Each payment application builds on the one before it, so accuracy is crucial. Before submitting, double-check all of your numbers.

Reply



Leave a Reply.

Follow us on facebook!